Dolores Park construction update

Dolores Park Works reports:

Completion of the North Side of the Dolores Park improvement project is now expected to be early 2015, a 4 month delay. Jake Gilchrist, manager for the project told us that unforseen problems were discovered during excavation of the foundation for the new maintainance shed. Excessive ground water was uncovered and had to be extracted before the contractor could continue and the soil then had to be reinforced to stabilize the area.

When the north side is finally done, the south side will be closed off and slowly improved too. The whole thing is still supposed to be done by late 2015. Read on for more info and pics.